GLOBAL MODEL PRE-IMPLEMENTATION CHECKLIST (list last modified 14 April 2006)
note: tbd = 'to be done' in table below!
| TASK # | Task pending | Task completed |
|---|---|---|
| 1 | NCEP Model Implementation team formed - (EMC) | February 2006 |
| 2 | NCEP Model Implementation noted at NCEP 'synergy' meeting - (EMC) | 27 February 2006 |
| 3 | Retrospective case studies | started in mid-March 2006 |
| 4 | Send Project Charter to NCO - (EMC) | 13 April 2006 |
| 5 | Notify NCEP Centers and determine POC (Points of Contact) - (NCO) | - |
| 6 | Pass '1st guess' GFS software to NCO - (EMC) | - |
| 7 | Make initial contact with Center POC's to determine desired output (graphics or data) - (EMC) | - |
| 8 | Create Parallel Web site for output (e.g. see MESO-branch's site as guide click here) - (EMC) | - |
| 9 | Establish 16-day real time parallel - 0-384hr (NCO) | - |
| 10 | Place test GEMPAK datasets on the TOC server to facilitate POC evaluations - (NCO) | - |
| 11 | Center POC's make real time evaluation - (NCEP Centers) | - |
| 12 | Pass final version GFS software to NCO - (EMC) | - |
| 13 | Coordinate with NWSH (DRG) on any data format/size impacts - (NCO) | - |
| 14 | Brief NCEP Director on results. Obtain permission to implement - (EMC,NCO) | - |
| 15 | Preparation of Information Statement for NWSH - (NCO) | - |
| 16 | Implementation - (NCO) | - |